Live Snag Register
Your name will be shown on comments, photos and status changes you make.
Yale locks currently left in unlocked / unrestricted fingerprint state
Curtain motors supplied do not support the agreed gesture operation (confirmed before ordering)
Up/down blind mechanism not integrating with automation — still needs a remote
Joint call with architects and Rahul Sethi (Casa Aurum) re curtain motors & automation
Staircase audio pending
Night lights not connected to automation
Wardrobe drivers not installed
Curtain cove lighting not installed
Under-vanity lighting not installed
Under-vanity lighting not connected to automation
Vestibule lights not working
Lobby downlights not working
Clean all lighting coves
Remove paint marks from lighting coves
Remove dark spots from lighting coves
Fix lifted lighting coves
Tower bolt insulation pending wherever requested
Door stoppers pending
Angle restrictors pending
Internal wooden handrail should terminate at the first step
Handrail between floors is bent
Fire detectors pending
IPBX pending
Ajax security system pending
Yale lock configuration pending, including TF lobby
Yale 100 NXT locks not configured
Yale fingerprints need configuring
Yale passwords need configuring
Yale Bridge response is very slow
Frosted film pending
Lift display/call button pending
Lift bronze mirror pending
Bug meshes pending
Remaining curtains pending
Curtain motor automation issues unresolved
Staircase wallpaper pending
Sprinkler positioning not fine-tuned
Noris bell switches in guest bathrooms not installed
Internal glass vendor to remove excess silicone
Internal glass vendor to rectify rattling glass
All paint finishing works
All paint cleaning / touch-ups
All skirting fixing works
Wall moulding repairs & finishing
All door corner filling & finishing
All AC controllers fixing
All switch socket blankers
All toilet mirrors installation
Master toilets steam installation works
Master toilets smoke detector fixing
Master toilets wardrobe & light works
Master toilets lights automation
Lift lobby trap door painting
Staircase handrail finishing
Staircase corner edge finishing
Staircase wallpaper base
Staircase speaker channel cutting & fixing
All flooring threshold works
All switch socket connection rectification & sticker installation
Lift pit paint & finishing works
Shower cubicle rectification
Remaining light installations
Lift moulding edges finishing
Living Room: POP pending
Living Room: AC grills pending
Living Room: powder washroom pending
Living Room: stone work pending
Living Room: wooden moulding pending
Living Room: WC pending
Living Room: vanity pending
Living Room: basin pending
Living Room: faucet pending
Living Room: wall sconces pending
Living Room: wallpaper pending
Day Room: wooden moulding pending
Day Room: wallpaper pending
Day Room: flooring pending
Day Room: desk pending
Day Room: unit behind desk pending
Day Room: TV pending
Ground Floor TV installation pending
Entry cove not working
Kitchen main ceiling light not connected to automation
Kitchen store incomplete
LV Room AC automation
First Floor master washroom downlight permanently ON for the last 10 days
First Floor audio installation pending
First Floor master lobby — two cove lights not working
First Floor lobby door mechanism not installed
First Floor panel door has no operating hardware installed
FF & SF lobby doors Georgian bar fixing
FF balcony railing coating
FF balcony railing coping lights
FF lounge fan automation connection
FF lounge ceiling finishing
FF window paint finishing
FF vestibule trap door painting
FF vestibule lights
FF dresser lights
FF lobby door tower bolt fixing
FF guest room toilet door lock
FF dresser door Georgian bar fixing
FF kids room electrical & lighting works
FF Master Lounge RO angle valve check
FF rear balcony stone work
FF & SF balcony tile cleaning
FF Master vestibule architrave breaking
Tarana & Kids toilet glass brick edge T-profile
FF & SF shower cubicle door frames silicone
FF & SF vestibule threshold stone work
FF Master Lounge AC controller shifting
SF staff beds fabricated as four instead of approved two
SF staff beds overdue
SF Guest Room AC not restarting
SF all door locks not working
Shower cubicle for Tarana washroom not yet ordered
Shower curtain required for SF nanny washroom
Second Floor audio installation pending
Lighting in SF nanny room is inadequate
SF Tarana room hardware pending
SF Tarana washroom hardware pending
SF Tarana room final paint coat pending
Wallpaper below SF pantry pending
Delay penalty to be imposed (SF staff beds)
SF guest room damaged door jamb/architrave requires rectification
Mandir chandelier pending after POP support
SF balcony railing coating
SF balcony ceiling finishing & painting
SF balcony lights & railing coping lights
SF lounge lights cleaning
Mandir fan installation
Mandir cove POP filling & finishing
Mandir door film
Mandir windows paint finishing
SF vestibule stone polishing
SF vestibule trap door painting
SF vestibule lights
SF vestibule wallpaper base
SF dresser smoke detector fixing
SF dresser window-side lights
SF dresser door corner skirting
SF toilet window film
SF Tarana door locks
SF Tarana AC grille
SF toilet pending vanity works
SF lobby door tower bolt patti
SF guest room flooring stone
SF guest room skirting stone gap
SF guest room grooves
SF guest room door lock chip replacement
SF DB panel MMAI fixing
SF Tarana toilet vanity stone work
SF Mandir ceiling plywood fixing
MMAI architrave breaking
Connect jacuzzi
Rectify jacuzzi tiles
Increase tread depth of jacuzzi steps
Install stainless steel entry handrail at jacuzzi
Jacuzzi vendor to complete final connections
Carry out complete jacuzzi testing
Put jacuzzi pumps onto automation
Put jacuzzi filtration onto automation
Put jacuzzi heater onto automation
Provide automation switch plate/interface for jacuzzi pumps, filtration & heater
Terrace parapet covering pending
Pipes around jacuzzi pending
Jacuzzi window to be replaced by window vendor
Plantation around jacuzzi pending
Third floor powder washroom incomplete
Third floor staff area incomplete
Staff pantry pending
Staff basin counters pending
Staff faucets pending
Lighting in staff areas pending
Wall fans in staff areas pending
Lighting levels in Third Floor staff areas need review
Third Floor lobby door requires improved locking
Rear camera wire shifting still pending despite repeated reminders
Front driveway drain broke after one vehicle
Outdoor lights not connected to automation
Spike light samples pending
Step light sampling pending
Outdoor camera points not at marked positions
Outdoor cameras pending
Fountain pending
Outdoor furniture pending
Grass pending
Service passage tiling pending
Front stone cleaning pending
Wind Seal coating pending
Rear courtyard incomplete
Rear metal doors pending
Earthing pending
House nameplate pending
Service passage door not installed
MS fabrication for service passage door has not started
Generator exhaust ducting pending
Generator ventilation ducting pending
Drain cover missing
Drain cover requires powder coating
Automated gate power supply from guard room pending
Rear metal gate access arrangement pending
Exterior paint junctions finishing
Main gate drain change
Canopy covering top
First Floor balcony outdoor strip lighting not installed
First Floor master balcony threshold stone jambs not installed
First Floor master balcony stone coping not installed
Balcony tile grouting requires rectification
Balcony handrails are not straight
Gaps in balcony wooden handrail joints need filling and polishing
Gym structure pending
Gym rear glass pending
Gym front glass pending
Gym electrical pending
Gym AC pending
Gym false ceiling pending
Gym flooring pending
Garage light sampling pending
Garage door pending
Wallpaper for Tanya wardrobe dresser pending
Wall sconces for Tanya wardrobe dresser pending
Popcorn lights for Raya and Vardaan pending
Cigar lounge panelling pending
Cigar lounge ceiling to be ordered
Cigar lounge chandelier pending
Custom lampshades to be ordered
Art selection pending